The BSH issued the planning approval decision for the offshore grid-connection “BorWin6 and BorWin kappa”on 08 October 2025 based on Section 45 of the Offshore Wind Energy Act in the version applicable until 31 December 2022 in connection with Section 74 of the Administrative Procedure Act in the version applicable until 31 December 2023.
A digital copy of the planning approval decision together with the established planning documents is available in the time of from 17 November 2025 up to and including 01 December 2025 published on the website of the Federal Maritime and Hydrographic Agency under ‘Announcements’. For more information, please refer to today’s announcement on the BSH website.